Tashir Group will build a 50 MW thermal power plant on the territory of Hrazdan TPP in Armenia, costing about €30 million, creating 25 jobs, with completion by end of 2024. The plant will use MAN Energy Solutions equipment.
Tashir Group will build a 126 MW thermal power plant in Noyemberyan, Armenia, costing over $120 million, creating 150 jobs, with construction starting in 2023 and lasting about two years.
| Site | Largest | Latest |
|---|---|---|
| Hrazdan TPP, Armenia | $33.0M | 2022-04-06 |
| Noyemberyan, Armenia | $120.0M | 2022-04-06 |