RheinEnergie selected MAN Energy Solutions to supply a 150-MW riverine heat-pump system at its Cologne-Niehl power plant, a roughly EUR 280 million project to deliver climate-neutral district heating.
RheinEnergie commissioned MAN Energy Solutions to deliver a turnkey 150 MW river-water heat pump plant at its Cologne-Niehl power plant site. RheinEnergie is investing about €280 million, with operation expected from 2027.
Aalborg Forsyning placed a follow-up order with MAN Energy Solutions for an additional seawater heat pump unit, bringing the Aalborg district heating plant to four units and 177 MW of heating capacity. The plant is scheduled to cut up to 210,000 tons of CO2 annually.
MAN Energy Solutions will supply a large-scale heat pump system with two 12.5 MW compressors to Scout Motors for its electric vehicle plant in Blythewood, South Carolina. The plant, part of a multi-billion Volkswagen investment, is designed for over 200,000 vehicles a year.
MAN Energy Solutions has signed a contract with Karpowership to deliver 48 MAN 18V51/60DF dual-fuel engines for its power plant ships, adding about 1,000 MW of capacity. MAN will also supply control systems and electromechanical equipment.
Yinson ordered nine radial compressor strings and two screw compressor strings from MAN Energy Solutions for an FPSO vessel operated by Azule Energy at the Agogo field, about 180 km west of Angola.
MAN Energy Solutions received three orders from Aker Solutions and Aibel for seven compressor systems for Aker BP's Hugin A, Munin and Valhall PWP-Fenris platforms in the Norwegian North Sea.
Air Products awarded MAN Energy Solutions an order for six air-compressor trains for the air-separation unit of its Clean Energy Complex in Darrow, Louisiana, which will produce blue hydrogen and blue ammonia. The article is dated July 17, 2023.
MAN Energy Solutions won an order from Air Products for six air-compressor trains for an air-separation unit at Air Products' Clean Energy Complex in Darrow, Louisiana. The complex will produce blue hydrogen and blue ammonia and is expected to start commercial operation in 2026.
MAN Energy Solutions was selected by Yinson to deliver 11 compressor trains for the Agogo FPSO vessel off Angola, operated by Azule Energy, with delivery planned during 2024.
MAN PrimeServ, the after-sales unit of MAN Energy Solutions, won a contract from Matson to retrofit the 7S90ME-C main engine of the containership Daniel K. Inouye into a 7S90ME-GI engine capable of running on LNG and fuel oil.
Equinor has awarded MAN Energy Solutions a contract to supply a subsea compressor unit for the Åsgard gas field offshore Norway, to be developed and tested in Zurich with delivery planned for March 2023.
MAN Energy Solutions subsidiary DWE won an order from Wanhua Chemical to deliver three salt-operated reactor systems for a new maleic anhydride plant in China, with an overall capacity of 200,000 tons per year. The plant produces PBAT for biodegradable plastics.
MAN Energy Solutions won a contract from Aker Solutions to supply five subsea HOFIM compressor units for Chevron's Jansz-Io compression project off Western Australia, which supports gas recovery at the Gorgon LNG project.
Aker Solutions awarded MAN Energy Solutions a contract to supply five Subsea HOFIM compressor units for Chevron's Jansz-Io Compression project offshore Western Australia, part of the Gorgon gas development.
Aker Solutions confirmed a major contract from Chevron to supply an all-electric subsea gas compression system for the Jansz-Io field offshore Western Australia, booked as about NOK 7 billion order intake in Q2 2021.
Modec ordered six compressor trains from MAN Energy Solutions for the Sangomar field offshore Senegal, with ready-for-installation expected in Q4 2021. The contract value was not disclosed.
MODEC has commissioned MAN Energy Solutions to supply five radial compressors and two screw compressor trains for the FPSO vessel serving Equinor's Bacalhau field off Brazil. The FPSO will process up to 220,000 barrels of crude oil and 15 million cubic meters of gas per day.
MAN Energy Solutions was awarded a contract to engineer three RG compressor trains for the Porthos carbon capture, utilization and storage project in the Netherlands, which will store about 2.5 million tons of CO2 per year under the North Sea.
MAN Cryo, part of MAN Energy Solutions, signed a contract to supply LNG fuel-gas supply systems and MAN Energy Solutions will supply dual-fuel engines for two RoRo newbuildings at Yantai Raffles shipyard in China for Wallenius SOL. Delivery is scheduled for 2021.
MAN Energy Solutions received an order from Estonian TSO Elering AS for two MOPICO compressor systems for the Balticconnector gas pipeline, to be installed at Paldiski and Puiatu in Estonia with delivery planned for summer 2019.
MAN Energy Solutions won an order to supply 18 MAN B&W 9S50ME-C9.6 main engines for nine RoRo vessels for Grimaldi Group, to operate in the Mediterranean. Hyundai Heavy Industries will build the engines and Jiangsu Jinling Shipyard will build the vessels, with delivery from 2020.
CSSC-MES Diesel placed the first order for MAN's ETB40 EGR blowers, to be installed on vessels built with several MAN B&W 7G60ME-C9.5 two-stroke main engines.
MAN Energy Solutions launched its ETB40 electrical turbo blower for exhaust gas recirculation at a ceremony in Shanghai, hosted by its two-stroke licensee CSSC-MES Diesel. The blower supports IMO Tier III compliance.