Vallourec was awarded a major contract by Subsea7 to supply about 130 km of carbon steel line pipe, over 15,000 tons, plus thermal insulation coating for Petrobras' Sepia 2 pre-salt project in the Santos Basin offshore Brazil.
Burckhardt Compression obtained two orders linked to the Boaventura Energy Complex, a major Petrobras project in Itaboraí, Rio de Janeiro, to supply six process gas compressor packages and related services.
Burckhardt Compression secured two orders from EPC companies for six process gas compressor packages and related services for Petrobras's Boaventura Energy Complex in Itaboraí, Rio de Janeiro. The orders support natural gas processing and new refining and lubricant units.
Burckhardt Compression received two orders from EPC firms to deliver six process gas compressor packages and services for three projects at Petrobras' Boaventura Energy Complex in Itaboraí, Rio de Janeiro.
Burckhardt Compression received two orders for six PL2 compressor packages and related services for Petrobras's Boaventura energy complex in Itaboraí, Rio de Janeiro. The orders came from EPC contractors running three parallel projects at the site.
NOV Inc. announced a $200 million investment over three years to roughly double the capacity of its subsea flexible pipe manufacturing facility in Açu, Brazil. Additional capacity is planned to come online in late 2029.
Halliburton announced that Petrobras awarded it multiple contracts for intelligent completions, electric safety valves and stimulation services in Brazil's deepwater fields, with work expected to begin in 2026.
Sulzer has won an order to supply multiple water injection pump packages to Seatrium for Petrobras next-generation P-84 and P-85 floating production vessels.
Sulzer will supply integrated water injection pump skids to Seatrium for Petrobras' P-84 and P-85 floating production vessels to be deployed in the Atapu and Sépia fields off Rio de Janeiro. The order was announced on 27 November 2025.
Sulzer was awarded a contract to supply integrated pump skids, including water injection and booster pumps, for two FPSO vessels being built by Seatrium for Petrobras. Delivery of the pump packages is scheduled for early 2026. The article is dated 26 November 2025.
Sulzer won an order from Seatrium to supply integrated water injection pump skids for Petrobras' P-84 and P-85 FPSOs, which will operate in the Atapu and Sepia fields off Rio de Janeiro. Delivery is scheduled for early 2026.
SLB secured a Petrobras contract to deliver services and technology for up to 35 ultra-deepwater wells in Brazil's Santos Basin, covering phase two of the Atapu and Sépia fields. Completions work is expected to start in mid-2026.
SLB won a Petrobras contract to provide completions services and technology for up to 35 ultra-deepwater wells in the Atapu and Sépia fields of the Santos basin, Brazil. Work is scheduled to begin in mid-2026.
Vallourec was awarded a long-term Petrobras contract to supply seamless OCTG pipes and VAM premium connections plus services for offshore wells in Brazil from 2026 to 2029, worth up to USD 1 billion.
Finland's Valmet signed a nationwide agreement to supply spare parts for Neles valves, actuators and positioners across all Petrobras units in Brazil. The initial term is one year with renewal options up to five years, and the value was not disclosed.
Seatrium selected Siemens Energy to supply electric motor-driven compression systems for Petrobras's FPSO vessels P-84 and P-85, under a contract valued at about R$2 billion. Operations are scheduled to start in 2029.
ABB was awarded an order by Seatrium to supply electrical equipment and automation for two new FPSO vessels, P-84 and P-85, for Petrobras in Brazil's Atapu and Sépia fields.
Norwegian firm TMC Compressors was contracted to supply a large marine compressed air system for Petrobras' Mero 3 FPSO, to operate in the Santos basin offshore Brazil. The contract value was not disclosed.
Baker Hughes secured a multi-year fully integrated completions systems contract from Petrobras, awarded in an open tender, to optimize production across multiple deepwater fields in Brazil, with delivery starting in late 2025.
Baker Hughes won a major multi-year fully integrated completions systems contract from Petrobras, following an open tender, to supply technology for deepwater offshore fields in Brazil.
Petrobras awarded SLB's OneSubsea joint venture a contract, after a competitive tender, for two subsea raw seawater injection systems for the Búzios field offshore Brazil. The systems will support FPSOs P-74 and P-75.
Petrobras awarded SLB's OneSubsea joint venture a contract for two subsea raw seawater injection systems for the Búzios field offshore Brazil, following a competitive tender. The systems will support FPSOs P-74 and P-75.
SLB's OneSubsea joint venture was awarded a contract by Petrobras to supply two subsea production manifolds, an electro-hydraulic distribution unit and related services for the Roncador field in the Campos Basin, offshore Brazil.
Vallourec has signed a significant contract with Petrobras to supply premium OCTG tubes and services for the Sepia 2 and Atapu 2 pre-salt projects. Deliveries of up to 25,000 tons over three years will come from its Brazilian plants.
TechnipFMC was awarded two subsea contracts by Petrobras for Brazil's pre-salt fields: a substantial contract for riser flexible pipe and a significant contract for subsea production systems for Atapu 2, Sepia 2 and Roncador, to be manufactured locally.
Petrobras has awarded NOV Flexibles a $350 million pipe contract, with NOV expecting to manufacture nearly all subsea equipment in Brazil at its Açu Port plant in Rio de Janeiro state.
SLB OneSubsea has secured a Petrobras contract to supply subsea production systems and services for the Atapu and Sepia ultra-deepwater fields in the Santos Basin offshore Brazil. Equipment will be produced at its Brazilian facilities.
SLB OneSubsea, a joint venture of SLB, Aker Solutions and Subsea7, secured a Petrobras contract for subsea production systems for two ultra-deepwater fields offshore Brazil, with FPSOs expected to start producing from 2029.
SLB OneSubsea has won a Petrobras contract to supply pre-salt subsea production systems and services for the second development of the Atapu and Sepia fields in Brazil's Santos basin, with much equipment produced locally in Brazil.
Vallourec has secured a contract to supply Petrobras with 1,800 tonnes of premium carbon steel tubes with GRE liners and CRA accessories, plus related services, for offshore wells in the Campos pre-salt basin. The products will be manufactured at Vallourec's plant in Barreiro, Minas Gerais, Brazil.
Petrobras has contracted Seatrium O&G Americas to supply two new FPSOs, P-84 for Atapu and P-85 for Sépia, in the presalt Santos Basin offshore Brazil. First oil is targeted for 2029-2030.
TechnipFMC was awarded the iEPCI contract for Petrobras's Mero 3 HISEP carbon capture project, which moves CO2-rich dense gas separation and storage to the seabed. The project is the culmination of a six-year R&D effort.
Baker Hughes secured a multi-year contract from Petrobras for integrated well construction services in the Buzios Field offshore Brazil, using three rigs, with work starting in the first half of 2025.
Baker Hughes has won a significant multi-year contract from Petrobras for integrated well construction services at the Búzios offshore field in Brazil, covering drilling, drill bits, wireline, cementing and related services across three rigs. Work is set to start in the first half of 2025.
Valaris has been awarded a 1,064-day contract for drillship VALARIS DS-4 with Petrobras offshore Brazil, worth approximately $519 million, starting late in Q4 2024.
TechnipFMC was awarded a major integrated EPCI contract by Petrobras to deliver the subsea HISEP carbon dioxide separation and injection project in Brazil's pre-salt Mero 3 field. The contract is worth over $1 billion according to the company's definition of major contracts.
Prysmian Group was awarded a contract by the Libra consortium led by Petrobras for about 60 km of steel tube umbilicals for the Mero 1 offshore oilfield in the Santos basin. The umbilicals will be manufactured at Prysmian's Vila Velha unit.
Prysmian signed a contract worth R$530 million (about EUR 100 million) with Petrobras to manufacture electro-hydraulic umbilicals, produced end-to-end at its Vila Velha plant with deliveries from 2024 to 2027.
Prysmian Group was awarded a contract by Petrobras to supply 350 km of deep-water electro-hydraulic umbilicals with steel tube and thermoplastic technology, plus offshore services. The contract is worth about 92 million euros and deliveries run from 2022 to 2025 from Prysmian's Vila Velha centre.
Baker Hughes was awarded a contract by Modec to supply gas technology and turbomachinery, including LM2500 gas turbine generators and steam turbine generators, for the BM-C-33 FPSO in the Campos Basin pre-salt, Brazil, developed by Equinor with Repsol Sinopec Brasil and Petrobras.
Chevron Lummus Global was awarded a Petrobras contract for a new 12,580 bpd hydroisodewaxing unit at the GasLub Hub lubricant plant in Itaboraí, Rio de Janeiro state. Its scope covers the technology license, basic design engineering and research unit testing.
OneSubsea, a unit of SLB, has secured contracts to supply 16 Christmas trees for Petrobras' Buzios 10 project, and multiphase pumps for the Atlanta field operated by Enauta and the Wahoo field operated by Prio, all offshore Brazil. The contract values were not disclosed.
OneSubSea announced new supply contracts to provide equipment to Petrobras, Enauta and PRIO, including 16 subsea Christmas trees for Petrobras' Buzios 10 project in the Santos Basin, with further units for Mero.
Baker Hughes Masoneilan shipped a package of API-6A severe service control valves for the Mero-3 FPSO in the Santos Basin, offshore Brazil, with the valves built at its Conde, France facility. Production on the field is expected in 2024.
SAIPEM awarded Baker Hughes more than 250 Consolidated pressure relief valves, including high-pressure API 10/15k valves, for the Petrobras P-79 FPSO at the Búzios field. The FPSO is due for delivery in 2025.
Aker Solutions was awarded a five-year frame agreement by Petrobras and partners to supply subsea production systems and lifecycle services for Petrobras-operated fields offshore Brazil, with up to 33 subsea trees estimated. The agreement runs from Q4 2022 to Q4 2027.
Saipem awarded Baker Hughes an EPC subcontract for over 250 Consolidated Pressure Relief Valves, including API 10/15k valves, for the P-79 FPSO being built for Petrobras in the Búzios field, delivery scheduled for 2025.
SAIPEM awarded Baker Hughes over 250 Consolidated pressure relief valves for the Petrobras P-79 FPSO in the Búzios field, Santos Basin. Delivery of the platform is scheduled for 2025.
Saipem selected GE Power Conversion to develop the Electrical Module for Petrobras' P-79 FPSO for the Buzios field off Brazil. The module will be fabricated in Asia, delivered in 2023 and the FPSO is scheduled to start operations in 2025.
Keppel Offshore & Marine selected Siemens Energy to provide power generation and compression packages for Petrobras' P-78 FPSO in Brazil's Búzios field. Equipment will be built at Siemens Energy's Santa Barbara d'Oeste facility, with delivery slated for 2023.
TMC Compressors has been contracted by Brazilian shipowner OceanPact to deliver marine compressed air systems for two anchor handling tug supply vessels working under Petrobras contracts. The deal value was not disclosed.
PJ Valves (PJV) was awarded two FPSO valve contracts for projects in Brazil's Santos and Campos basins, including the Buzios and Mero 3 FPSOs. The contracts are reported as worth $11 million in total.
TechnipFMC signed three frame agreements with Petrobras to manufacture more than 500 km of flexible pipe over four years for Brazilian brownfield developments, worth between $500 million and $1 billion.
TMC Compressors has been selected to supply a large marine compressed air system for the Mero-3 FPSO, destined for the Libra block offshore Brazil. The system will be manufactured in Europe. The contract value was not disclosed.
Aker Solutions has won a substantial contract from Petrobras to supply a subsea production system and related services for the Mero 4 project offshore Brazil. Installation is scheduled for 2023 to 2025.
Yinson Holdings received two letters of intent from Petrobras to supply the FPSO for the Integrado Parque das Baleias project offshore Brazil. The contract period is 22.5 years, valued at $5.2 billion, with production scheduled to start in Q4 2024.
Prysmian Group was awarded a contract by Petrobras to supply 350 km of deep-water electro-hydraulic umbilicals, worth about EUR 92 million. Production and delivery will run from 2022 to 2025 at its Vila Velha center in Brazil.
TechnipFMC has secured a new subsea contract from Petrobras for the Búzios 6-9 fields offshore Brazil, to supply subsea trees, controls, distribution units, topside systems and installation support. Delivery is expected to begin in the first quarter of 2023.
TechnipFMC has been awarded a subsea contract by Petrobras for the Búzios 6-9 fields in the Santos basin offshore Brazil, reported as worth between $250 million and $500 million. Delivery is expected to begin in the first quarter of 2023.
Petrobras signed a $2.3 billion EPC contract with a Saipem and DSME joint venture to supply the P-79 FPSO for the Buzios field in Brazil's Santos Basin, with delivery scheduled for 2025.
TechnipFMC secured a significant subsea contract from Petrobras to supply up to eight manifolds with robotic valve controllers for the Marlim and Voador fields offshore Brazil. The contract is valued between $75 million and $250 million.
Baker Hughes has been awarded two flexible pipe contracts by Petrobras covering up to 322 km of pipe for five offshore fields in Brazil, including Sapinhoá, Tupi, Marlim 2 and Itapu. The announcement was reported January 7, 2021.
TechnipFMC's all-electric Robotic Valve Controller has operated since February 2020 on a subsea water and gas injection manifold for Petrobras in the Tupi pre-salt field, Santos Basin, off Rio de Janeiro, under a contract to deliver robotic manifolds.
China's Neway Valve signed a supplier contract with Modec Offshore Production Systems Singapore, a Petrobras contractor, to deliver valves for an offshore oilfield project in Brazil, worth about USD 25 million, with delivery by March 2021.
Sandvik won a contract to supply more than 500 km of super duplex stainless steel umbilical tubes, encapsulated by Prysmian, for Brazil's Mero pre-salt oilfield in the Santos Basin. The order is for the Mero 1 phase, operated by the Libra Consortium.
A consortium led by Petrobras awarded Prysmian Group a contract to supply about 60 km of steel tube umbilicals for the Mero 1 ultra-deepwater project in the Libra area offshore Brazil. Oil production is expected to begin in 2021.
Orseal supplied the valve package for the FPSO Guanabara MV31, chartered by Petrobras for the Libra consortium's Mero field in the Santos Basin off Brazil. The first valve delivery has been completed, with more contracts for the vessel to follow.
Weatherford has won its largest-ever contract for deep-set safety valves from Petrobras, to deliver 24 Optimax safety valves over the next four years. The valves are rated up to 10,000 psi and setting depths down to 12,000 ft.
Aker Solutions is developing low-cost wet Christmas trees at its Parana plant, designed to be up to 30% more competitive, with the project developed with Shell and Petrobras and expected to be ready in two years.
Velan ABV, a Velan subsidiary in Lucca, Italy, received a contract extension from MODEC to supply riser and topside actuated valves and compact manual ball valves for the FPSO MV31 Guanabara, deployed at the Mero field operated by Petrobras. Deliveries are due mid to late 2019; the article gives a combined value of US$63 million for two contracts.
TechnipFMC won an engineering, procurement, construction and installation contract from Petrobras for the Mero 1 pre-salt field offshore Brazil, with production expected to start in 2021. The contract value is reported as a range of 500 million to 1 billion dollars.
Petrobras has contracted Aker Solutions to supply a subsea production system and services for the Mero 1 project in the presalt Santos basin offshore Brazil. Equipment deliveries are scheduled for 2020.
Aker Solutions signed a contract with Petrobras to supply a subsea production system and services for the Mero 1 project in Brazil's pre-salt area, with deliveries scheduled for 2020. The contract value was not disclosed.
Siemens Power and Gas, including Dresser-Rand, received an order for four SGT-A35 gas turbine power generation packages and two DATUM CO2 compressor packages for MODEC's Sépia FPSO in Brazil. Siemens will also provide long-term service and maintenance.
Siemens Power and Gas, including Dresser-Rand, received an order from MODEC for four SGT-A35 gas turbine power packages and two DATUM CO2 compressor packages for the Sépia FPSO. Siemens will also provide long-term service and maintenance; delivery is scheduled for late 2018.
Fluxo Soluções, a Brazilian distributor, obtained a new CRCC supplier certificate from Petrobras, dated December 2017, to represent the Masoneilan and Consolidated valve brands of Baker Hughes in Brazil's oil and gas market.