Suntar Membrane Technology Co Ltd completed the expansion of the Baicheng wastewater treatment plant, increasing capacity from 80,000 m³/d to 100,000 m³/d. The project cost 63.0477 million yuan.
Suntar Membrane Technology and Shaanxi Water Group Sewage Treatment Co. signed a strategic cooperation framework agreement on April 14, 2021 in Xi'an. They plan to establish an R&D center for membrane materials and wastewater resource utilization, a wastewater treatment O&M company, and a membrane product and equipment manufacturing company.
Suntar Membrane Technology has signed a CNY188 million EPC contract with Jiangsu Jiatong Energy, a subsidiary of Tongkun Group, for a wastewater treatment plant. The project is expected to be completed by May 15, 2023.
| Site | Largest | Latest |
|---|---|---|
| Baicheng, China | $8.76M | 2024-03-21 |