Loading…
Rusatom Infrastructure Solutions (part of Rosatom) is modernizing the Severskaya CHPP in Seversk, Russia, with a total investment of nearly 9 billion rubles. A new 60-ton boiler drum from Barnaul Boiler Plant has arrived, and the project includes reconstruction of 10 boilers and installation of two new steam turbines, to be completed by 2026.
Rusatom Infrastructure Solutions plans to continue modernizing Seversk CHPP in 2023, with new turbines scheduled for mid-2023, and total investment exceeding 8 billion rubles by 2026.
The modernization of the Seversk CHP plant, started in 2020 by Rosatom subsidiary RIR, is on schedule. The 8 billion ruble project includes installing two turbines and replacing 10 boilers by 2025.
| Site | Largest | Latest |
|---|---|---|
| Seversk, Russia | $104.0M | 2023-10-24 |