GE secured an order from Caithness Energy to supply 7HA.02 gas turbines, heat recovery steam generators, and steam turbine generators for the 1.875GW Guernsey Power Station in Guernsey County, Ohio. The plant is scheduled for completion in Q4 2022.
GE Power secured a contract to supply 7HA.02 gas turbines, heat recovery steam generators, and steam turbine generators for Caithness Energy's 1.8GW Guernsey Power Station in Guernsey County, Ohio. The contract also includes a multi-year services agreement and digital solutions. The project is expected to be completed in Q4 2022.
Gemma Power Systems received notice to proceed with engineering, procurement, and construction of a 1,875 MW natural gas-fired power plant in Guernsey County, Ohio, with completion scheduled in 2022.
Gemma Power Systems, a subsidiary of Argan Inc., received full notice to proceed on an EPC contract with CPV Basin Ranch Holdings for the 1,350 MW CPV Basin Ranch Energy Center in Ward County, Texas. Construction is expected to begin in fall 2025 with completion in 2028.
Gemma Power Systems has received limited notice to begin preliminary design and site preparation for the 1.8 GW Guernsey Power Station in Ohio, being jointly developed by Caithness Energy and Apex Power Group. Full construction is expected to start in spring 2019 with completion in 2022.
GE and Caithness Energy have entered into an exclusive agreement to pursue development of multiple new combined-cycle power plants in the U.S. GE will deliver equipment valued at over $1 billion, including up to six HA gas turbines and six steam turbines.
GE and Caithness Energy signed a multi-plant agreement worth $1 billion for HA turbines.
GE and Caithness Energy announced an exclusive agreement to develop multiple HA combined-cycle power plants in the US. The equipment package could exceed $1 billion and includes up to six HA gas turbines. Plants are projected to be developed throughout 2017 and 2018.