May 11, 2018CONTRACTCairo, Egypt, Egypt MHPS selected to renew four boilers at Cairo West Power Station
Mitsubishi Hitachi Power Systems (MHPS) has been awarded a contract by CEPC to renew four power generation boilers with a combined capacity of 1,360 MW at the Cairo West Power Station in Egypt.
Productspower generation boilers
“Under the contract, MHPS will renew four existing power generation boilers, with combined generation capacity of 1,360MW.”nsenergybusiness.com
- 2 sources
- nsenergybusiness.comMHPS selected to renew four boilers at Cairo West Power Station in Egypt - NS EnergyKondapuram Sampangi Archana RaniMay 11, 2018
- power.mhi.comMHPS Signs Contract with CEPC for Rehabilitation Project of Cairo West Power Station in Egypt -- Rehabilitation Project to Ensure Stable Operation and Greater Reliability of Four Natural Gas and Heavy Fuel Oil-fired Boilers -- | Mitsubishi PowerMay 11, 2018