Mitsubishi Generator received orders for six gas turbine generators for the Rumah-1 and Al-Nairyah-1 power plants in Saudi Arabia, with a total output of 3,600 MW, to be supplied with Mitsubishi Heavy Industries gas turbines. Operations are scheduled to commence in 2028.
Mitsubishi Generator has received an order for two generators for a gas turbine power plant to be constructed in Ouazzane Province, Morocco. The Al Wahda Power Plant, planned by ONEE and built with China Energy Engineering Corporation, will have a total capacity of 990 MW and is expected to begin operations in 2027.
Mitsubishi Generator will supply a gas turbine generator for a new 475 MW cogeneration power plant in Jubail, Saudi Arabia, developed by a consortium led by TAQA and JERA. The plant will provide electricity and steam for the SATORP petrochemical complex expansion.
Mitsubishi Generator Co., Ltd. received an order for 2 units of generators for a 500MW gas turbine combined cycle power plant in Miri, Sarawak, Malaysia, owned by PETROS Power Sdn. Bhd. The plant is planned to commence operations in 2027.
Mitsubishi Electric and Mitsubishi Heavy Industries completed the integration of their power-generator systems businesses under Mitsubishi Generator Co., Ltd., which commenced operations on April 1, 2024.