Machine-Building Factory of Podolsk (ZiO Group) signed a contract with GEH Engineering LLC to supply two heat-recovery boilers for a 330 MW thermal power plant in Chulman, Yakutia. The contract was signed in September 2023, with delivery by April 2025.
ZiO Group of Companies, under a contract with PJSC RusHydro, shipped over 750 tons of boiler equipment for the reconstruction of Vladivostok TPP-2. The project includes three new boiler units and will increase the plant's electric capacity to 574 MW and thermal capacity to 1,115 Gcal/h.