Main equipment for the 200 MW Combined Cycle Power Plant (CCPP) Pancevo has been delivered and a steam turbine generator installed. The plant is expected to be completed before Q3 2020.
Gazprom energoholding (GEH) plans to buy power equipment manufacturer REP Holding from Gazprombank. The parties are expected to sign the main terms of the deal on October 3, 2019.
Gazprom Energoholding completed installation of two 200 MW gas turbines at the combined heat and power plant in Pancevo, Serbia, under a EUR40 million agreement with Ansaldo. Commissioning is planned for 2020.
Gazprom Energoholding completed installation of two Ansaldo AE64.3A gas turbines at the 200 MW Pancevo combined cycle power plant in Serbia. The turbines were delivered under a €40 million agreement signed in March 2018. The plant is planned for commissioning in 2020.
Construction of the Pancevo combined-cycle thermal power plant began in March 2019, with commercial operations expected in 2020. The €180 million ($209 million) plant will have 208MW electric capacity and 121 GCal heat capacity.
Siemens is considering buying out Power Machines' stake in their joint venture Siemens Gas Turbine Technologies (STGT) and then selling 50% to Gazprom Energoholding (GEH). The deal would aim to achieve full localization of gas turbine production for thermal power plant modernization, with GEH as anchor customer.
| Site | Largest | Latest |
|---|---|---|
| Pancevo, Serbia | $44.7M | 2019-12-12 |