Sinoma-CBMI is modernizing the Ciments du Sahel plant in Kirene, Senegal, with a new 6000 tpd clinker line (SC3 project). Two ball mills weighing 208t each have been installed. The project costs EUR 245 million and broke ground in December 2020.
BUA Cement signed a $1.05 billion agreement with Sinoma CBMI to construct three cement plants in Edo, Sokoto and Adamawa states, each with 3 million tonnes per annum capacity, to raise total capacity to 20 million tonnes by end of 2022.
BUA Cement signed an agreement with Sinoma CBMI to build three new cement plants of 3Mta each in Edo, Sokoto and Adamawa states, Nigeria. The $1.05 billion project will bring BUA's total capacity to 20Mta and is expected to be completed by end of 2022.
Central African Cement Company and Sinoma CBMI have signed an agreement to set up a cement factory in Ndola, Zambia, at a total cost of $480 million. The plant will produce 2 million tons of cement per year and create 1000 jobs during construction. Construction will commence in April 2019.
| Site | Largest | Latest |
|---|---|---|
| Kirene, Senegal | $295.0M | 2021-05-13 |