A consortium led by Chantiers de l'Atlantique, with GE Grid Solutions and SDI, received a confirmed order to design, build and install the electrical substation for the Calvados offshore wind farm off Courseulles-sur-Mer, France. The 450 MW wind farm will have 64 turbines, with substation installation in 2023 and commissioning in 2024.
“Atlantique Offshore Energy, la Business Unit dédiée aux Energies Marines de Chantiers de l’Atlantique, leader d’un consortium formé avec GE Grid Solutions et SDI, filiale de DEME Group, vient de recevoir la confirmation de la commande du groupement constitué d’EDF Renouvelables, Enbridge et wpd offs”saintnazairenews.fr