Chantiers de l'Atlantique, with GE Grid Solutions and SDI, was awarded a contract by Eoliennes Offshore des Hautes Falaises and Eoliennes Offshore du Calvados to design, manufacture and install electrical substations for the Fécamp and Courseulles-sur-Mer offshore wind farms off Normandy, France.
Chantiers de l'Atlantique cut the first steel for the electrical substation (S34) for the Saint-Nazaire offshore wind farm, the first in France. The substation will be delivered in 2021 for the 480 MW park developed by EDF and Enbridge.
GE Renewable Energy has started production of 80 Haliade 150-6MW wind turbines for the Saint-Nazaire offshore wind farm in France, under a contract with Eolien Maritime France. Nacelle assembly begins Q2 2020, with installation and commissioning scheduled for 2022.