Loading…
Shanghai Electric Power Station Group won the order for the main equipment of the Waigaoqiao power plant expansion replacement 2×1000 MW coal-fired project, with the first unit scheduled for commissioning in June 2027 and the second in August 2027.
Shanghai Electric Power Station Group won a contract to supply the complete main equipment for the Yuezhou 2×1000MW coal-fired power plant project in Yueyang County, Hunan Province. The project is scheduled for completion in the first half of 2027.