Bladt Industries and Semco Maritime will jointly supply two offshore substations for the Baltic Power wind farm offshore Poland. The substations weigh 2,500 metric tons each and the wind farm is due for completion in 2026.
Smulders and Haizea Bilbao signed a Selected Supplier Agreement to cooperate on the supply and fabrication of over 70 transition pieces for the Baltic Power offshore wind farm in the Polish Baltic Sea.
A consortium of Semco Maritime and Bladt Industries was awarded an EPCI contract by Baltic Power sp. Z.O.O. (a joint venture of Northland Power and PKN Orlen) for two 650 MW offshore substations in the Baltic Sea, 20 km north of Lubiatowo, Poland. The project runs from 2022 to 2026.