Siemens Energy announced it will build a combined cycle power plant on a turnkey basis in Ostiglia, Lombardy, Italy for utility EP Produzione. The plant will have an installed electrical output of 880 MW and is scheduled for completion in spring 2025. Siemens Energy will supply an SGT5-9000HL gas turbine and other equipment.
The RTI consortium of Siemens Energy, Fata and Demont was awarded an EPC/turnkey contract for the engineering, procurement and construction of a new 881 MW combined cycle gas turbine unit at the Ostiglia power plant in Italy.
FATA, in consortium with Siemens Energy and Demont, signed an EPC contract on February 19, 2022 with EP Produzione to build an 880MW combined cycle power plant in Ostiglia, Italy, with commissioning scheduled for February 2025.
Demont was awarded a contract by Ansaldo Energia for the mechanical assembly of a gas turbine, generator and auxiliaries at the Iren plant in Turbigo, Italy. The announcement was made on May 6, 2021.
Demont was awarded a contract by Ansaldo Energia for the assembly of the recovery boiler for the construction of the New Combined Cycle TL 400 at the Iren plant in Turbigo, Italy. The work includes mechanical and electro-instrumental assembly of the steam generator, piping, and chimney.