T Plus signed contracts for the supply of main equipment for the modernization of the fourth unit of Izhevsk CHPP-2, with a total equipment cost of nearly 3.2 billion rubles. Suppliers include Ural Turbine Works, TKZ Krasny Kotelshchik, Energeticheskiy Standart, and ELSIB.
PJSC MMK commissioned a new 50 MW turbine unit at its Central Power Plant in Magnitogorsk, Russia, increasing the plant's capacity by 25 MW. The turbine was produced by Ural Turbine Works and the generator by Elsib.
Novosibirsk-based ELSIB manufactured a new 12MW turbogenerator for KOKS as part of a power plant expansion. The unit was shipped on December 5, 2018, with commissioning planned for Q2 2019.
A new turbogenerator produced by ELSIB was installed at Pavlodar CHP-3 on September 8, 2018, increasing the station's capacity by 15 MW. The generator replaced an older unit and has a capacity of 125 MW.