PJSC ArcelorMittal Kriviy Rih is proceeding with the final stage of construction of two new continuous casting machines (CCM Nos. 2, 3) at its plant in Kriviy Rih, Ukraine. The $144 million project will add annual capacity of 1.4 million tons each, with hot tests of CCM No. 3 planned for Q3 2018 and final commissioning in Q1 2019.
| Site | Largest | Latest |
|---|---|---|
| Kriviy Rih, Ukraine | $144.0M | 2018-07-24 |