Louisville Gas and Electric Company and Kentucky Utilities Company broke ground on Mill Creek 5, a 640-MW natural gas combined-cycle generating unit at the Mill Creek Generating Station in Louisville, Kentucky. The unit is expected to begin powering customers in 2027.
Louisville Gas and Electric Company and Kentucky Utilities Company ordered a 7HA.03 combined-cycle plant from GE Vernova for the Mill Creek Generating Station in Louisville, Kentucky. The 645 MW plant will replace two aging coal units.
GE Vernova received an order from LG&E and KU for 7HA.03 combined-cycle plant equipment to power a new 645MW natural gas generating unit at the Mill Creek Generating Station in Louisville, Kentucky. The unit will feature GE's 7HA.03 gas turbine with hydrogen capability.
GE Vernova received an order from LG&E and KU for a 645-MW hydrogen-ready 7HA.03 gas turbine to replace two coal units at Mill Creek Generating Station in Kentucky. The new combined cycle plant will be built by TIC (Kiewit).
Suez will design and supply wastewater treatment systems for Louisville Gas and Electric Company and Kentucky Utilities at coal-fired power stations near Louisville, Kentucky, treating Flue Gas Desulfurization wastewater.
| Site | Largest | Latest |
|---|---|---|
| Louisville, United States | 2024-11-14 |