Tangshan Sanyou Yuanda Fiber Co., Ltd. is undertaking a 60,000 tonnes/year functional viscose staple fiber technical renovation project at its site in Tangshan Nanpu Economic Development Zone, China. The project involves an investment of CNY 302 million and will increase total capacity to 330,000 tonnes/year.
Tangshan Sanyou Yuanda Fiber Co., Ltd. is proceeding with a 200,000 tonnes/year functional and differentiated viscose staple fiber project in Hebei, China, and has issued a tender for electrical installation work for a 35KV substation. The project involves two 100,000 t/y production lines.
| Site | Largest | Latest |
|---|---|---|
| Tangshan Nanpu Economic Development Zone, China | $45.5M | 2017-11-08 |
| Hebei, China | 2017-06-05 |