Budimex SA, Mitsubishi Power Europe, and Tecnicas Reunidas reached a settlement with PGE Górnictwo i Energetyka Konwencjonalna to increase the contract value for the Turów power plant unit by 107.97 million PLN net and extend the completion deadline to April 30, 2021.
“Wartość umowy została podwyższona... o kwotę 107.972.832,00 złote netto”kieruneksurowce.pl