St James's Hospital in Dublin has signed a 20-year Energy Performance Contract with Veolia, targeting €26 million in savings and 118,380 tonnes of carbon reduction. The contract includes installation of a 2MWe CHP plant, LED lighting, and other energy upgrades. Work started in July 2020 and will be completed by December 2021.