TenneT has awarded a joint venture of Engie Fabricom and Iemants (a Smulders subsidiary) a contract to construct an offshore transformer station for the Hollandse Kust Noord wind farm zone. The station includes a 45-meter-high jacket and a 4,100-tonne topside. Engineering has started, with construction beginning in October 2020 and load-out planned for fall 2021 (jacket) and spring 2022 (topside).
“TenneT has selected the joint venture EngiE Fabricom – Iemants (subsidiary of Smulders) to construct an offshore transformer station for the Hollandse Kust (Noord) wind farm zone.”windtech-international.com