Wärtsilä received an order from Rofeica Energia to supply a Wärtsilä 34SG gas engine generating set for a 9.1 MW CHP plant in Barcelona, Spain. The order was placed in April 2020 and the conversion is expected to be completed by end of 2020.
“The 9.1 MW plant will be delivered on a fast-track basis as the gas conversion is expected to be completed before the end of 2020.”wartsila.com