Aggreko will provide a hybrid modular power station combining solar, battery and thermal generation for Resolute Mining's Syama gold mine in Mali, replacing the existing 28MW diesel plant. Stage 1 (30MW thermal + 10MW battery) targets completion in 2020; Stage 2 (additional 10MW thermal + 20MW solar) by 2023.
“Work on the new plant will commence in the current quarter, and once fully operational, Resolute expects it to reduce Syama's power costs by approximately 40%.”miningmagazine.com