Loading…

Edison and Ansaldo Energia signed a contract for a new combined gas cycle at the Marghera Levante power plant in Porto Marghera, Italy. The €300 million investment includes a GT36 gas turbine, making the plant the most efficient in Europe with 63% efficiency and 780 MW capacity.
“The overall investment amounts to more than 300 million euros, which will also be used to create the power island, made up mainly of the GT36 gas turbine developed by the Genoese company.”ansaldoenergia.com
Summarized from public sources; check the original articles before acting on it.