Babcock & Wilcox received full notice to proceed on a $2.4 billion design-build agreement with Base Electron to deliver 1.2 GW of new generation capacity using four 300-MW natural gas boilers and steam turbine generators. Siemens Energy will supply the steam turbine generator sets.
“Receiving full notice to proceed for this $2.4 billion project further underscores the strategic role B&W plays in supporting the rapidly expanding power needs of large‑scale AI data centers”babcock.com
Summarized from public sources; check the original articles before acting on it.