GameChange Energy began foundation work on a 300,000-sq-ft high-voltage transformer factory near Mumbai, India, designed to produce up to 150 medium and large power transformers annually, rated up to 300 MVA and 500 kV. Production is expected to begin in Q1 2028, with most output destined for U.S. customers.
GameChange Energy broke ground on a major expansion of its transformer manufacturing operations in Mumbai, investing in a new 300,000-square-foot EHV transformer factory. The factory will produce EHV Power Transformers rated up to 300 MVA and 500 kV, with planned annual capacity of 150 transformers. Production is scheduled to begin in Q1 2028.
| Site | Largest | Latest |
|---|---|---|
| Mumbai, India | 2026-08-18 | |
| Taloja, India | 2026-08-18 |