Vertiv entered a contract with EcoDataCenter to provide 96 Vertiv Liebert PCW chilled water cooling units for two new data center facilities in Falun, Sweden, with a total capacity of about 12 MW. The facilities are to be commissioned at the start of 2025.
Vertiv has been awarded a contract by EcoDataCenter to supply 96 Vertiv Liebert PCW chilled water cooling units with a total capacity of around 12 MW for two new data centres in Falun, Sweden, expected to be commissioned in early 2025.