GE Gas Power has completed a temporary reserve power plant consisting of eight TM2500 trailer-mounted gas turbines at its Birr, Switzerland facility, generating up to 250 MW for the Swiss Federal Office of Energy. The contract was signed in September 2022 and the plant reached commercial startup in April 2023.
The Swiss Federal Office of Energy ordered eight GE TM2500 aeroderivative gas turbines (250 MW total) for a temporary reserve power plant at GE's Birr site in Switzerland. The plant is expected to run from February 2023 to April 2026.