Sintek Group signed an agreement with Medcem to build a new integrated production line with a clinker capacity of 9,000 tons/day, part of a $230 million investment. Sintek's scope is $128 million for construction, mechanical equipment, and commissioning.
Medcem chose Sintek Group to build a new 9000t/day production line at its integrated Mersin cement plant in Turkey. Sintek Group's part of the project has a budget of US$128m. Commissioning is scheduled for early 2023. Announced on 6 October 2021.
Sintek has signed a contract with Medcem for a new integrated production line in Turkey with a clinker production capacity of 9000tpd.
Sintek signed a contract with Medcem for a new integrated cement production line in Turkey with a clinker capacity of 9000 tonnes per day, costing approximately US$230 million. Sintek's contract is valued at nearly US$128 million.