Gamuda Bhd has secured a RM1.97 billion contract from Pengurusan Air Selangor to be the main contractor for Package 1 of the Rasau water treatment plant project, including design and build of an intake structure and water treatment plant.
Taliworks Corp Bhd has won a RM602.43 million contract from Pengurusan Air Selangor to design and build a water pumping station and mains for Phase 1 of the Sungai Rasau water treatment plant in Malaysia. The project is expected to be completed by December 31, 2024.
Air Selangor and Indah Water Konsortium signed an agreement to form a special purpose vehicle, Central Water Reclamation Sdn Bhd (Air Selangor 60%, IWK 40%), to produce non-potable treated water for industrial customers in Klang Valley. The first project in Setia Alam involves a RM15 million investment and a 7.5 MLD capacity plant expected to start operations by Q2 2021.