Caterpillar Inc. agreed to supply six Cat G20CM34 gas generator sets and other equipment for a 58 MW power plant repower at NorthWestern Energy's Huron Generating Station in South Dakota. Construction began in July 2020, with commercial operation expected by end of 2021.
NorthWestern Energy awarded Caterpillar a contract to supply six Cat G20CM34 gensets and other equipment for a 58-MW addition to the Huron power plant in South Dakota, part of an $86 million upgrade. Construction starts July 2020, commercial operation expected end of 2021.
NorthWestern Energy will begin construction in July 2020 on an $84 million, 58-megawatt natural gas-fired generation plant near Huron, South Dakota.
| Site | Largest | Latest |
|---|---|---|
| near Huron, United States | $84.0M | 2020-05-12 |