Loading…
Siemens Industrial Turbomachinery (Sweden) supplied the first gas turbine for the Novopolotsk Cogeneration Plant's 100MW peak-reserve power source, with the second turbine due by end of May 2021. The project is part of a plan to build 800 MW of peak-reserve capacity at four sites in Belarus.
Minskenergo and Siemens Industrial Turbomachinery AB signed a contract for the supply of gas turbines and related services for energy facilities in Minsk Oblast, as part of integrating the Belarusian nuclear power plant into the national grid.