An industrial park will be built on the site of Shadrinsk Auto Aggregate Plant (SHAZ) in Shadrinsk, Russia, with construction starting in Q2 2021 and full capacity by 2024, costing about 300 million rubles.
AO Shadrinsk Auto-Aggregate Plant (SHAZ) has installed a new 10-ton overhead crane in its workshop for manufacturing load-haul-dump machines (LHDs), along with new pipe bending and turning machines. The crane was supplied by Srednevolzhsky Crane Plant. The plant is also completing assembly of a second 14-ton LHD and plans to produce up to 50 units of underground equipment per year at full capacity.
Shadrinsk Auto-Aggregate Plant (ShAAZ), part of UMMC, has started construction of an assembly shop for underground mining load-haul-dump machines (LHD). The first phase investment is about 120 million rubles, and the shop is planned to open in 2020.
| Site | Largest | Latest |
|---|---|---|
| Shadrinsk, Russia | $4.00M | 2020-12-04 |