NZT Power and the Northern Endurance Partnership awarded engineering, procurement and construction contracts worth about £4 billion across eight packages to nine firms for the Teesside East Coast Cluster carbon capture project, subject to final investment decisions planned for September 2024.
Servelec Controls, using HIMA safety systems, won the control and safety systems for two National Grid compressor station upgrade projects at Huntington and Peterborough, working with contractor Costain.
Servelec Controls was awarded several contracts via Costain to develop integrated control and safety systems for two new National Grid compressor stations at Huntingdon and Peterborough.
Costain has been awarded a £113 million contract by National Grid to upgrade its Peterborough and Huntingdon gas compressor stations, with work running to 2021. The scope covers detailed design, decommissioning, build and recommissioning.