Osisko Gold Group selected Epiroc to supply drill rigs and jumbos for its Cariboo Gold Project in British Columbia. The total underground mobile equipment fleet is valued at approximately $43 million, with initial deliveries expected in late 2026 and the majority arriving in 2027.
Osisko Gold Group provided a construction update on its Cariboo Gold Project in British Columbia, Canada. The project is on schedule for first gold pour in Q1 2029 and commercial production in H2 2029, with cumulative costs of $355 million incurred and remaining budget of ~$907 million.
| Site | Largest | Latest |
|---|---|---|
| central British Columbia, Canada | $940.0M | 2018-05-25 |