Siemens received a contract from Pampa Energía SA to convert the Genelba simple cycle gas-fired power plant to combined cycle, increasing capacity from 168 MWe to about 364 MWe. Commissioning is scheduled for mid-2019.
Siemens, with partner Techint, received a contract from Pampa Energía to expand the Genelba gas-fired power station in Marcos Paz, Buenos Aires Province, Argentina, converting it to a combined cycle plant and increasing capacity from 168 MW to about 364 MW. The plant is scheduled to be commissioned in mid-2019.
Wärtsilä inaugurated the 100 MW Pilar thermal power plant in Argentina on August 31, 2017, built for Pampa Energía. The plant uses six Wärtsilä 50DF multi-fuel engines running on natural gas and heavy fuel oil.