Siemens Gas and Power signed a contract with Kazanorgsintez for the turnkey construction of a 250 MW combined cycle power plant in Tatarstan, Russia, plus two long-term service agreements with Kazanorgsintez and Nizhnekamskneftekhim. Total value is approximately €290 million.
JVIS, a US automotive components supplier for Ford, Chrysler, Toyota, Mercedes and BMW, has tested and approved plastic from Nizhnekamsk, Tatarstan, and is ready to order up to 15,000 tons per year. The company is working on logistics and may also represent TAIF in the North American market.
Siemens signed a €380 million contract with Taif Group to build a 495 MW combined cycle power plant in Tatarstan, Russia. Siemens will supply two gas turbines, one steam turbine and power distribution equipment. The plant is scheduled for completion by May 2021.
Linde has been awarded a major contract by PJSC Nizhnekamskneftekhim (NKNK) to supply an olefin plant in Nizhnekamsk, Tatarstan. The first stage will produce 600,000 t of ethylene and over 600,000 t of other chemical products per year, with capacity to be doubled later. The plant is scheduled to go on stream in 2022.
The first GE 9HA gas turbine in the Russia/CIS region entered operation at the Kazan CHP-3 power plant in Tatarstan, adding 405 MW and doubling the plant's capacity from 385 MW to 790 MW. The project was delivered by GE with Gama Power Systems for customer TGK-16 (TAIF group).