JSHP held a foundation stone laying ceremony on September 30, 2019 for a $100 million campus expansion to increase production capacity for solar and wind transformers to 1,000 units per month.
JSHP will design, fabricate, test and deliver a 345kV 110MVAR shunt reactor and a 345kV 160MVA transformer for the Bayonne Energy Center Phase II, with a 36-week lead time.
| Site | Largest | Latest |
|---|---|---|
| Liyang City, China | $100.0M | 2019-09-30 |