Mech-Tool Engineering received a contract valued at over $9 million from Technip to supply external walls for Gravity Based Structure 1 on Novatek's Arctic LNG project. The walls will be supplied to Bomesc Offshore Engineering's yard in Tianjin, China.
Mech-tool Engineering has secured a series of major new contracts to build refinery substations at AV Dawson's North Sea Supply Base in Middlesbrough, with the first 287-tonne substation exported to Central Asia. The company has a programme of planned construction projects up to at least 2020.
Mech-Tool Engineering Ltd has been awarded a GBP 37 million contract by Wood Group to deliver a field operations office module and twenty remote instrument enclosure modules. The delivery will take place from now until 2019, and the contract has created 20 new jobs.