UAB Baltic valves technologies, a Kaunas-based SME, was awarded a EUR 3,000,000 contract to supply stop valves and components to UAB Ignitis grupės paslaugų centras in Lithuania. The award decision was dated 23 June 2026 and the notice was published on 12 August 2026.
MT Group signed a contract with Everllence Switzerland, formerly MAN Energy Solutions, for a 5 MW high-speed electric compressor with magnetic bearings for the Jauniunai compressor station in Lithuania, in partnership with Amber Grid.
JPackaging has begun construction of a wooden pallet and pallet collar plant in the Šeduva industrial park, Lithuania, under a construction contract worth nearly €14 million with AB Panevėžio statybos trestas. Total investment reaches €30 million and up to 150 jobs are planned.
Voith Hydro won the general contractor order to install a fifth 110 MW variable-speed pump turbine unit at Ignitis Gamyba's Kruonis pumped storage hydropower plant in Lithuania. Ignitis Gamyba is investing around EUR 150 million in the expansion, with operation expected by the end of 2026.
FlexBlow is adding a new 3,500 sq m manufacturing facility to its 10,000 sq m site in Kretinga, Lithuania, to increase capacity for its FlexBlow8 hybrid stretch blow molding machines, with production expected from July 2019.
Panevezio Statybos Trestas AB signed a contract with Roquette Amilina AB to construct a production building for EUR 1.748 million including VAT, with completion scheduled for August 2019.
UAB Grigeo Packaging, a subsidiary of AB Grigeo, agreed to take over the corrugated cardboard production business from its parent company to meet growing demand. The business continues operating from Grigiškės.