Siemens was awarded a contract by Chinese EPC contractor Sepco III to supply an industrial steam turbine package that converts the Az Zour South 3 open cycle plant in Kuwait into a combined cycle plant, adding 263MW without extra gas. The combined cycle plant is expected to operate in mid-2019.
“Siemens has been awarded a contract to deliver an industrial steam turbine package to expand the Az Zour South 3 open cycle gas turbine power plant to a combined cycle power plant.”constructionweekonline.com