Elektrownia Ostrołęka sp. z o.o., part of the Enea Group, concluded the public contract awarding procedure for the construction of Ostrołęka Power Plant C (approx. 1,000 MW), selecting a consortium of GE Power Sp. z o.o. and Alstom Power System S.A.S. as general contractor for PLN 5,049,729,000 net.
“The Management Board of ENEA S.A. hereby informs that on 4 April 2018 it gained knowledge of the conclusion by the company Elektrownia Ostrołęka sp. z o.o. of the public contract awarding procedure under the name 'Construction of Ostrołęka Power Plant C with approx. 1,000 MW power output'.”ir.enea.pl