Loading…
ENKA entered into a consortium agreement with GE on January 3, 2017, to undertake the Samawa Combined Cycle Power Plant project, awarded by the Ministry of Electricity of Iraq under a contract dated February 5, 2017. The EPC contract covers design, construction, and commissioning of a 750 MW combined cycle power plant in Samawa, Iraq.
“ENKA entered into a consortium agreement with General Electric (GE) on January 3rd 2017, to undertake works on the Samawa Combined Cycle Power Plant project which was awarded to GE by the Ministry of Electricity of Iraq under a contract dated February 5 th 2017.”enka.com
Summarized from public sources; check the original articles before acting on it.