JSW Energy is expanding its KSK Mahanadi thermal power plant in India by 1,800 MW (a 600 MW unit and 1,200 MW balance), with capex per MW estimated 25-30% below industry average due to shared infrastructure. The 600 MW unit is on track for FY28 and the 1,200 MW for FY29.
“This brownfield configuration underpins its estimate of capex per MW at least 25%-30% below the industry average.”multibagg.ai