Valmet has been selected by Metsä Group to supply a 3D Fiber molded fiber production line for its Äänekoski mill in Finland. Start-up is scheduled for 2028.
Valmet will supply a 3D Fiber moulded fibre production line for Metsä Group's mill in Äänekoski, Finland, with nominal output above 100 million items a year and start-up planned for 2028.
Valmet announced an order from Metsä Group for a 3D Fiber molded fiber packaging line to be installed beside the Muoto demo plant in Äänekoski, Finland, with start-up planned for 2028. Contract value was not disclosed.
BUTTING Anlagenbau received an order for containers and pipeline construction for Stora Enso's O750 Oulu project, which converts a paper machine in Oulu, Finland into a packaging board line producing about 750,000 tonnes per year. Production is expected to start in early 2025.
Stora Enso has awarded Voith a contract to convert a former coated paper machine at its Oulu, Finland site into a board machine producing folding boxboard and coated kraft back with 750,000 tons per year capacity. Start-up is scheduled for early 2025.
Stora Enso has commissioned Voith to convert a former paper machine at its Oulu site in Finland into a board machine producing 750,000 tons per year of folding boxboard and coated kraft back. Start-up is scheduled for early 2025.
Valmet will deliver BCTMP, evaporation and NCG technology plus a mill-wide automation package for Stora Enso's Oulu mill in Finland, part of a roughly EUR 1 billion board line conversion. The order value was not disclosed and the upgraded mill is scheduled for early 2025.
Valmet will supply new reel and winding technology and surrounding equipment to modernize board machine KK 1 at Metsä Board's Kyro mill in Finland, with start-up scheduled for the second half of 2021. The order value was not disclosed.
Valmet will supply a multifuel CYMIC circulating fluidized bed boiler and a flue gas treatment plant to Oulun Energia's new 75 MW biopower plant in Laanila, Oulu, replacing the Toppila unit I. The orders, worth around EUR 70 million, will be included in Valmet's Q1 2018 orders.