The Samsung Engineering and CTCI joint venture SCJV was awarded Package 1 of QatarEnergy's Ras Laffan Petrochemicals Project, covering a 2.08 million tonne ethylene unit and utilities. The total project cost is stated as $6 billion.
“The SCJV was awarded Package 1, which is to build a 2.08 million tons ethylene production unit, utilities, and office facilities.”oilandgasmiddleeast.com