Hyundai Engineering submitted a proposal to extend the completion time of the Polimery Police polypropylene plant by 95 days and increase its fee by EUR 39.8 million. The plant is already producing polypropylene and propylene continuously.
“The General Contractor proposes to extend the completion time of the Polimery Police project by an additional 95 days and to increase the General Contractor's fee by EUR 39,772,455.”grupaazoty.com