PJSC Power Machines completed production of its first serial high-power gas turbine GTE-170 for the Nizhnekamsk CHPP. The company plans to produce two gas turbines in 2024, six in 2025, eight in 2026, and ten per year from 2027, with total investment of 25 billion rubles.
“Power machines completed the production of the first serial high-power gas turbine GTE-170 complete with a generator and waste heat boiler.”tek-all.ru